The Shoreham Herald reports that work is about to begin on the new bridleway that will allow users of the Downs Link to avoid having to cross the A283.
David Barling, county councillor for Bramber Castle, said ..
The underpass scheme is intended to provide a much better and safer route for walkers, cyclists and horse riders by removing the need to cross the open A283 bypass, which is extremely dangerous, you usually take your life in your hands crossing at this point.
Edburton Contractors, working for West Sussex County Council, is programmed to begin initial clearance works [today]. Mr Barling explained:
This means having a look at the site and clearing scrub and trees or tree roots that may need removal along the highway verge. This initial phase will take a couple of weeks and then proper construction works will start on Monday, August 18, and it is hoped that these will last no more than four weeks to complete. The finished pathways will then be left to settle down for a couple of weeks more and then [be] fully open to pedestrians, cyclists and horse riders.